Fire Safety Forms and Resources

 

Downloadable Resources

 

Fire Alarm Inspection Process

Contractor or Supplier Action or RequirementInspection or Procedure Required
Must have University of Arizona Fire Marshall approved Fire Alarm Shop Drawings.Must have pre-installation meeting with UA/FM Fire Safety.
Install all Fire Alarm raceway and junction boxes.Must have PDC electrical inspection before proceeding.
Device layout inspection.Must have UA/FM Fire Safety and Risk Management.
Receive Fire Alarm wiring and splicing class.Must receive this before proceeding.
Install and pull all fire alarm wire. All loops must be wired thru to check integrity.Must have UA/FM Fire Safety inspection before proceeding.
Meter all loops from Fire Alarm Panel box to check for opens, shorts, crossed circuits, and ground faults on all wiring.Must have UA/FM Fire Safety electrical inspection before proceeding.
Receive device addresses printed on drawings from Fire Alarm supplier.Must receive this before proceeding.
Install/connect all Fire Alarm devices for this project, to include pulls,smokes, heats, ducts, a/v's, v/o's, horns, bells, sprinkler monitors, all shutdown connections, and any other Fire Alarm related equipment.Must have UA/FM Fire Safety electrical inspection before proceeding.
Meter all loops from Fire Alarm Panel box to check for opens, shorts, crossed circuits, and ground faults on all wiring.Must have UA/FM Fire Safety inspection before proceeding.
Have Fire Alarm supplier install panel components and land field wiring, and trim out panel.Provide UofA with signal circuit loads,total stand by load and alarm load calculations. Must have UA/FM Fire Safety electrical inspection before proceeding.
Fire alarm supplier must provide proposed control software and device/circuit labels to UofA Fire Safety for approval before installation of software in Fire Alarm Control Panel.Must receive approval from Fire Safety before proceeding.
Contractor and supplier must successfully complete a NFPA 72 
test before calling for a UA/FM Fire Safety, contractor andProvide copy of contractor / supplier NFPA 72 test to PDC to call for
supplier NFPA 72 test to start commissioning run.UofA NFPA 72 test.
Contractor, supplier and UA/FM Fire Safety must successfully complete a NFPA 72 test before the five day commissioning run will start.A NFPA 72 test witnessed by UA/FM Fire Safety must be completed with no deviations before starting commissioning run.
After the successful completion of the commissioning run, then the University of Arizona Fire Marshall test can occur.UA/FM Fire Safety will confirm the commissioning run has completed with no troubles, supervisories or alarms.